A)
Laying road
B)
Laying pavement
C)
Underground passage
D)
On ground passage

Correct Answer :   Underground passage


Explanation : Tunnel can be defined as artificial underground passage, which is created for different purposes. It is required in case of highways, railways, sewerage and water supply.

A)
Full face method
B)
Drift method
C)
Top heading and benching method
D)
All of the above

Correct Answer :   All of the above

A)
Drilling and mucking can be done simultaneously
B)
Removal of muck from the heading is very easy
C)
Benching provides a plateform for working on heading
D)
None of the above

Correct Answer :   Removal of muck from the heading is very easy

A)
0.75 m
B)
0.60 m
C)
0.45 m
D)
0.30 m

Correct Answer :   0.60 m

A)
fan cut
B)
V-cut
C)
pyramid cut
D)
All of the above

Correct Answer :   All of the above


Explanation : * fan cut
* V-cut
* pyramid cut
* horizontal wedge cut

A)
soft ground
B)
firm ground
C)
running ground
D)
None of the above

Correct Answer :   soft ground

A)
soft rock
B)
running soil
C)
rock terrain
D)
None of the above

Correct Answer :   rock terrain

A)
Holes are drilled by pneumatically operated rock drills
B)
One drill is required for each 4 to 5 m² force area
C)
The diameter of the bore hole at the deepest point should be 6 mm more than the diameter of the cartridge
D)
All of the above

Correct Answer :   All of the above

A)
80% of the ruling gradient
B)
75% of the ruling gradient
C)
60% of the ruling gradient
D)
50% of the ruling gradient

Correct Answer :   75% of the ruling gradient

A)
the cherry picker
B)
the grass hopper method
C)
passing track method
D)
All of the above

Correct Answer :   All of the above


Explanation : * the cherry picker
* the grass hopper method
* passing track method
* California crossing, Dixon conveyor

11 .
For transferring the tunnel alignment through shafts, we adopt the following steps :

1. Hanging two or more plumb lines in the shaft
2. Determining the bearing of the plumb lines i.e. plumb plane
3. Suspending a 35 kg weight by each plumb line
4. Immersing the weights of both the plumb lines in the buckets containing water.

The correct sequence of steps is :
A)
1 2 3 4
B)
4 3 2 1
C)
1 3 2 4
D)
2 1 4 3

Correct Answer :   1 2 3 4

A)
one opening is provided
B)
two openings are provided
C)
three openings are provided
D)
no opening is provided

Correct Answer :   two openings are provided

A)
circular
B)
parabolic
C)
polycentric
D)
rectangular

Correct Answer :   polycentric

A)
blowing fresh air by ducts to the face of tunnel
B)
blowing fresh air and exhausting foul air by ducts
C)
exhausting foul air by ducts from the face of the tunnel and permitting fresh air through the tunnel
D)
All of the above

Correct Answer :   All of the above

A)
Shield method
B)
Linear plate method
C)
Compressed air method
D)
All of the above

Correct Answer :   All of the above


Explanation : * Shield method
* Linear plate method
* Compressed air method
* Mechanical tunneler i.e. mole method

A)
10 metres depth
B)
15 metres depth
C)
20 metres depth
D)
25 metres depth

Correct Answer :   15 metres depth

A)
poor
B)
highly fissured
C)
likely to get seepage of water
D)
All of the above

Correct Answer :   All of the above

A)
Oval line
B)
Centre line
C)
Spring line
D)
Middle line

Correct Answer :   Spring line


Explanation : Spring line is determined as the line at which the wall breaks from sloping outward to sloping inward toward the crown. This acts as a barrier between the outward and inward regions.

A)
Hydrological conditions
B)
Surface limits
C)
Climatic conditions
D)
Atmospheric conditions

Correct Answer :   Hydrological conditions


Explanation : The determination of the alignment for tunnel can be done based on geological and hydrological conditions, cross-section and length of the continuous tunnel, time of consideration and limit of the surface.

A)
Dixon conveyor method
B)
the grass hopper method
C)
the passing track method
D)
California crossing method

Correct Answer :   the grass hopper method

21 .
Pick up the correct statement from the following :
A)
The accuracy of 1 in 10, 000 is required for planimetric control
B)
The topographical maps of the Survey of India are useful in the mountainous region for tunnelling.
C)
1 second theodolite is used for angular measurement to achieve an angular error of 15 √N where N is number of angles
D)
All of the above

Correct Answer :   All of the above


Explaination : * The height point on the ridge is fixed with the help of reciprocal ranging
* The accuracy of 1 in 10, 000 is required for planimetric control
* The topographical maps of the Survey of India are useful in the mountainous region for tunnelling.
* 1 second theodolite is used for angular measurement to achieve an angular error of 15 √N where N is number of angles

A)
5 m to 6 m
B)
4 m to 7 m
C)
2.5 m to 6 m
D)
2 m to 4 m

Correct Answer :   5 m to 6 m

A)
the top
B)
the bottom
C)
the centre
D)
All of the above

Correct Answer :   All of the above


Explanation : * the top
* the bottom
* the centre
* the side

A)
5.5 m to 5.8 m
B)
5.8 m to 6.2 m
C)
6.7 m to 7.3 m
D)
7.3 m to 7.5 m

Correct Answer :   6.7 m to 7.3 m

A)
timber line
B)
cast iron lining
C)
Brick lining
D)
stone lining

Correct Answer :   cast iron lining

A)
tunnelling is preferred
B)
a open cut is preferred
C)
a detour round the hill is preferred
D)
All of the above

Correct Answer :   tunnelling is preferred

A)
450 particles/cm³
B)
400 particles/cm³
C)
300 particles/cm³
D)
250 particles/cm³

Correct Answer :   450 particles/cm³

A)
Driving of tunnel is done in two portions of its section
B)
Driving the top portion is done in advance of the bottom portion
C)
Firing of head holes is done just before the bench holes are fired
D)
After driving the top portion 3 m to 3.5 m holes are drilled into the head and bench

Correct Answer :   Firing of head holes is done just before the bench holes are fired

A)
dewatering
B)
foredrainage
C)
permanent drainage
D)
All of the above

Correct Answer :   All of the above

30 .
For initial surveys of tunnels, the following activities are involved :

1. Marking portal point with concrete pillars on the ground
2. Marking tunnel obligatory points on the topographical maps
3. Preliminary setting of the tunnel on the topographical Survey of India maps
3. Driving lines between the fixed obligatory points.

The correct sequence of the activities is :
A)
1 2 3 4
B)
3 2 4 1
C)
2 4 3 1
D)
4 3 1 2

Correct Answer :   3 2 4 1

A)
two sections
B)
three sections
C)
four sections
D)
five sections

Correct Answer :   three sections

A)
highways
B)
railways
C)
sewerage
D)
All of the above

Correct Answer :   All of the above


Explanation : * highways
* railways
* sewerage
* water supply project

A)
ammonia dynamite
B)
special gelatine
C)
semi-gelatine
D)
blasting gelatine

Correct Answer :   ammonia dynamite

A)
4.2 m to 4.5 m
B)
4.5 m to 4.8 m
C)
4.9 m to 5.5 m
D)
5.5 m to 5.8 m

Correct Answer :   4.9 m to 5.5 m

35 .
The following operations are required for tunnelling in rocky terrain :

1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking

The correct sequence is :
A)
1 2 3 4 5
B)
2 3 1 4 5
C)
2 3 5 4 1
D)
4 2 1 3 5

Correct Answer :   2 3 1 4 5

A)
avoidance of head on collisions
B)
facility in carrying out repairs
C)
economy in cost of construction
D)
All of the above

Correct Answer :   All of the above


Explanation : * avoidance of head on collisions
* facility in carrying out repairs
* economy in cost of construction
* provision of separate exit and entrance of two traffic streams

A)
muck box
B)
balle-ship
C)
U-bottom
D)
All of the above

Correct Answer :   All of the above


Explanation : * muck box
* balle-ship
* U-bottom
* side dump car

A)
continuous open drains
B)
concrete lining
C)
provision of longitudinal drains
D)
All of the above

Correct Answer :   All of the above


Explanation : * continuous open drains
* concrete lining
* provision of longitudinal drains
* grouting with cement or chemicals

39 .
Which of the following are percussion drills?

1. Shot drill
2. Diamond drill
3. Wagon drill
4. Churn drill
A)
1 and 2 are correct
B)
3 and 4 are correct
C)
1 and 4 are correct
D)
2 and 3 are correct

Correct Answer :   3 and 4 are correct

A)
Austrian method
B)
English method
C)
Army method
D)
Needle beam method

Correct Answer :   Austrian method

A)
Soft ground
B)
Rocky ground
C)
Firm ground
D)
Running ground

Correct Answer :   Rocky ground


Explanation : Tunneling has been classified based on the type of strata present. It includes firm ground, soft ground and running ground. These will determine the bearing capacity of the soil.

A)
Plotting
B)
Trenching
C)
Benching
D)
Back bearing method

Correct Answer :   Benching


Explanation : In case of no possibility of full face excavation, top heading method is adopted for having a better output. Benching process is also adopted for digging small tunnels

A)
Bents of steel
B)
Bents of iridium
C)
Bents of plastic
D)
Bents of aluminum

Correct Answer :   Bents of steel


Explanation : The provision of soft strata must be done for withstanding the excavation. It can be provided by bents of wood, bents of steel, liner plates and poling, which are placed to retain material between the adjacent bents.

A)
remains free from snow
B)
reduces the maintenance cost
C)
avoids interference with surface rights
D)
All of the above

Correct Answer :   All of the above


Explanation : * remains free from snow
* reduces the maintenance cost
* avoids interference with surface rights
* reduces the cost by reducing the route distance

45 .
The following tunnels were constructed in different countries for different purposes :

1. Emperor Claudius built the first Roman tunnel
2. The first highway tunnel was constructed in Hungary
3. The first underground railway tunnel was constructed in Great Britain
4. The first navigational tunnel was constructed in France.

The correct chronological development of these tunnels is:
A)
1 4 2 3
B)
2 3 1 4
C)
3 2 4 1
D)
4 1 3 2

Correct Answer :   1 4 2 3

46 .
The following operations are generally employed for tunnelling in hard rock.

1. Removing ground water,
2. Loading holes and firing the explosive
3. Setting up and drilling
4. Grouting and lining
5. Removing muck
6. Ventilation and removing explosion dust

The correct sequence is :
A)
3 4 6 1 5 2
B)
3 2 6 5 1 4
C)
4 1 2 3 6 5
D)
5 4 2 1 3 6

Correct Answer :   3 2 6 5 1 4

A)
Oxygen should not be less than 19.5%
B)
Carbondioxide should not be more than 0.5%
C)
Hydrogen sulphide should not be more than 0.001%
D)
All of the above

Correct Answer :   All of the above


Explanation : * Oxygen should not be less than 19.5%
* Carbondioxide should not be more than 0.5%
* Hydrogen sulphide should not be more than 0.001%
* Carbon mono-oxide should not be more than 0.01%

A)
Rod
B)
Shield
C)
Pole
D)
Jar born

Correct Answer :   Shield


Explanation : In the case of soft grounds, tunneling can be dangerous and cave-ins are common. To prevent this, an iron or steel cylindrical element called shield is placed in the soft soil, which can crave the hole perfectly.

A)
Tracing
B)
Benching
C)
Full face method
D)
Back bearing method

Correct Answer :   Full face method


Explanation : Rock tunneling involves the same principle as of the tunneling in the ground. Those include full face method, top heading method and drift method. Based on the conditions of the area, these can be adopted.

A)
trimmers
B)
easers
C)
chisels
D)
cut holes

Correct Answer :   trimmers

51 .
In the given figure drill holes, heading, mucking and benching are numbered as 1, 2, 3, 4; The correct sequence is :
A)
4, 1, 3, 2
B)
1, 2, 3, 4
C)
3, 4, 1, 3
D)
4, 1, 2, 3

Correct Answer :   4, 1, 3, 2

A)
42 D
B)
82 D
C)
104 D
D)
124 D

Correct Answer :   82 D

A)
Removal of top portion
B)
Removal of bottom portion
C)
Excavation of one drift in the centre
D)
Excavation being done along the periphery

Correct Answer :   Excavation being done along the periphery

A)
Placing rocks
B)
Recording values
C)
Marking profile
D)
Improving foul gases

Correct Answer :   Marking profile


Explanation : Rocky strata involve usage of blasting method for developing tunnels. The sequence contains marking profile, loading explosive, removing foul gases, checking, scaling, mucking and bolting.

A)
Fire-setting
B)
Tunneling
C)
Continuous blasting
D)
Sequential blasting

Correct Answer :   Fire-setting


Explanation : Blasting is the conventional method which is adopted in case of rock tunneling. In the case of fire-setting, tunnel is heated with fire and then cooled with water. Rapid expansion and contraction weakens and rock and tends to break.