Mechanical Engineering : Industrial Engineering and Production Management - Quiz(MCQ)
A)
When slack of an activity is zero, it falls only on critical path.
B)
CPM technique is useful to minimise the direct and indirect expenses.
C)
Critical path of a net work represents the minimum time required for completion of project.
D)
All of the above

Correct Answer : Option () :  