Earliest finish time can be regarded as
A)
latest finish time - duration of activity
B)
latest finish time + duration of activity
C)
earliest start time + duration of activity
D)
earliest start time - duration of activity

Correct Answer : Option (C) :   earliest start time + duration of activity