The essential condition for the decompression of an activity is that
A)
the project time should change due to decompression
B)
an activity could be decompressed to the maximum extent of its normal time
C)
after decompression the time of an activity invariably exceeds its normal time
D)
None of the above

Correct Answer : Option (B) :   an activity could be decompressed to the maximum extent of its normal time