Civil Engineering : Construction Management - Quiz(MCQ)
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is____.
A)
a+5m+b / 6
B)
a+4m+b / 6
C)
a+3m+b / 6
D)
a+m+b / 6

Correct Answer :   a+4m+b / 6