A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
A)
1500 m³
B)
1000 m³
C)
500 m³
D)
200 m³

Correct Answer :   1500 m³