Civil Engineering : Construction Management - Quiz(MCQ)
Earliest finish of an activity is always________.
A)
Less than earliest event time of the following node
B)
Greater than earliest event time of the following node
C)
Less than or equal to earliest event time of the following node
D)
Greater than or equal to earliest event time of the following node

Correct Answer :   Less than or equal to earliest event time of the following node