Civil Engineering : Estimating and Costing - Quiz(MCQ)
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
A)
0.200 m³
B)
0.247 m³
C)
0.295 m³
D)
0.274 m³

Correct Answer :   0.274 m³