Google News
logo
Civil Engineering : Construction Management - Quiz(MCQ)
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is_____
A)
15 days
B)
10 days
C)
9 days
D)
8 days

Correct Answer :   9 days