Civil Engineering : Construction Management - Quiz(MCQ)
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good____.
A)
D = EF - ES
B)
EF = ES + D
C)
LS = LF - D
D)
All of the above

Correct Answer :   All of the above


Explanation : * EF = ES + D
* LS = LF - D
* LF = LS + D
* D = EF - ES