Latest start of an activity is always_______.
A)
less than latest event time of preceding node
B)
greater than or equal to latest event time of preceding node
C)
equal to latest event time of preceding node
D)
less than or equal to latest event time of preceding node

Correct Answer :   greater than or equal to latest event time of preceding node