Pick up the correct statement from the following :
A)
CPM analysis is activity oriented
B)
PERT analysis is event oriented
C)
In CPM, the time is related to cost
D)
All of the above

Correct Answer :   All of the above


Explanation : * CPM analysis is activity oriented
* PERT analysis is event oriented
* In CPM, the time is related to cost
* CPM does not make any allowance for the uncertainties in the duration of time