Pick up the correct statement from the following :
A)
Optimistic time estimate refers to activities
B)
Most likely time estimate refers to activities
C)
Expected time estimate refers to activities
D)
All of the above

Correct Answer :   All of the above


Explanation : * Optimistic time estimate refers to activities
* Pessimistic time estimate refers to activities
* Most likely time estimate refers to activities
* Expected time estimate refers to activities