Civil Engineering : Concrete Technology - Quiz(MCQ)
The form work is usually removed after ________ for walls, columns, and the vertical faces of all structural components.
A)
72 hours
B)
56 hours
C)
24 hours
D)
24 to 48 hours

Correct Answer :   24 to 48 hours


Explanation : In all circumstances, 3/7 of the aforesaid period will suffice for rapid hardening cement, with the exception of vertical sides of slabs, beams, and columns, which should be held for 24 hours.