Civil Engineering : Concrete Technology - Quiz(MCQ)
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
A)
7 days for beam soffits
B)
14 days for bottom slabs of spans 4.6 m and more
C)
21 days for bottom beams over 6 m spans
D)
All of the above

Correct Answer :   All of the above


Explanation : * 7 days for beam soffits
* 14 days for bottom slabs of spans 4.6 m and more
* 21 days for bottom beams over 6 m spans
* 2 days for vertical sides of columns