Civil Engineering : Estimating and Costing - Quiz(MCQ)
While estimating a reinforced cement structure, the omitted cover of concrete is assumed
A)
in thin slabs, 12 mm minimum or diameter of the bar whichever is more
B)
at the end of reminforcing bar, not less than 25 mm or twice the diameter of the bar
C)
for reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
D)
All of the above

Correct Answer :   All of the above