JIRA Testing - Quiz(MCQ)
As part of the ____ process, the team is required to resolve a set of issues within a specified period of time.
A)
Sprint
B)
Issue
C)
Story
D)
Scrum

Correct Answer :   Sprint


Explanation : As part of the sprint process, the team is required to resolve a set of issues within a specified period of time.