Capacity Planning is done to balance the load at work center and you can calculate production capacity based on requirement of product as per available capacity.
You need to check capacity load on work center and if any work center is overloaded, we need to move orders to different work centers.
To check Capacity Loads
Use T-Code CM01 or go to Logistics →
Production →
Capacity Planning →
Evaluation →
Work Center View →
Load.