SAP Production Planning (PP) - Interview Questions
What is Schedule Margin key?
Schedule margin key is used to define the production order floats to determine the production dates in Production Order /Planned Order.
 
Opening period : The opening period represents the number of workdays that are subtracted from the order start date in order to determine the order creation date.
 
Float before production : It represents the number of workdays that are planned as a float between the start date (planned start date) and the production start date (target start date).
 
Float after production : The float after production should provide a float for the production process to cope with any disruptions so that there is no danger that the planned finish date will be exceeded.
 
Release period : The release period represents the number of workdays that are subtracted from the order start date in order to determine the production order release.