Correct Answer : All of the above
Correct Answer : 14 days
Correct Answer : Engineer
Correct Answer : heavy construction
Correct Answer : 1
Correct Answer : Minor works
Correct Answer : Initiation of proposal
Correct Answer : (tâ‚ - tâ‚‚) - t
Correct Answer : 50 %
Correct Answer : 9 days
Explanation : * CPM analysis is activity oriented* PERT analysis is event oriented* In CPM, the time is related to cost* CPM does not make any allowance for the uncertainties in the duration of time
Correct Answer : minor projects
Correct Answer : Bar chart method
Explanation : * Optimistic time estimate refers to activities* Pessimistic time estimate refers to activities* Most likely time estimate refers to activities* Expected time estimate refers to activities
Correct Answer : zero float
Explanation : * departmental representative or user* local civil authority representative* representative of engineer authority* representative of administration
Explanation : * effective command and control* defined responsibilities at all levels* rigid discipline in the organisation* ability of quick decision at all levels
Correct Answer : industrial construction
Correct Answer : concrete cured
Correct Answer : Programme Evaluation and Review Technique, is event oriented
Explanation : * site survey* availability of labour* study of specifications* availability of construction materials
Correct Answer : duration
Correct Answer : slow time
Correct Answer : instructions by the executive engineers
Explanation : * selection of site* acquisition of land* formalisation of alignment of work* formalisation of designs and preparation of estimate
Correct Answer : light construction
Correct Answer : minimum time
Correct Answer : 67% at the site and 33% under procurement
Explanation : * a circle* a square* a triangle* an ellipse
Correct Answer : Cheapest critical activity
Correct Answer : Less than X
Correct Answer : Free float
Correct Answer : Free float and independent float both must be zero
Correct Answer : float
Explanation : * preparation of estimates* preparation of specifications* initiating the procurement action of resources* taking remedial action for likely bottleneck in the execution
Explanation : * a project is divided into various activities* required time for each activity is established* sequence of various activities is made according to their importance* net work is drawn by connecting the activities and the events
Correct Answer : a+4m+b / 6
Correct Answer : dummy
Correct Answer : 1900
Correct Answer : line organisation
Correct Answer : Critical ratio scheduling
Correct Answer : 1940
Correct Answer : functional organisation
Correct Answer : horizontal lines
Correct Answer : Chief Engineer
Explanation : * EF = ES + D* LS = LF - D* LF = LS + D* D = EF - ES
Correct Answer : Activity
Correct Answer : 40 kg/tonne
Correct Answer : Reduce by 200 kg
Correct Answer : 900 kg
Correct Answer : Wet sticky clay
Correct Answer : 500 cum
Correct Answer : Slow time
Correct Answer : Dump truck
Correct Answer : 9 kg/tonne
Correct Answer : its earliest finish time and earliest start time for its successor activity
Correct Answer : 1, 2 and 4
Correct Answer : 1 and 4 are correct
Correct Answer : Rs. 8,43,750
Correct Answer : An event
Correct Answer : Sheep foot rollers
Correct Answer : On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Correct Answer : Less than or equal to earliest event time of the following node
Correct Answer : 2 and 3 are correct
Correct Answer : The soil survey, traffic survey, concept design and approximate cost
Correct Answer : Updating
Correct Answer : greater than or equal to latest event time of preceding node
Correct Answer : 75 and 83
Correct Answer : Rs. 3480
Correct Answer : Moist loam
Correct Answer : Hoe
Correct Answer : Loose sand
Correct Answer : Drag line
Correct Answer : (i) and (iii) are correct
Correct Answer : For all activities required to start the work at site on finalization of the contract document
Correct Answer : Variation in cost in materials element, labour element and petrol-oil-lubricant element
Correct Answer : Applying the theory' of probability to sample testing or inspection
Correct Answer : 1, 2 and 3 are correct
Correct Answer : 2.3% and 84.1%
Correct Answer : Increasing the direct cost and decreasing the indirect cost